Overdue Final Cost Reports

Final Cost Reports Due No Later than June 30, 2008

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/20/09 at 17:38:22




GILBERTSVILLE (MOUNT UPTON) CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-02-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




GILBERTSVILLE-MT. UPTON CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-02-02-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




EDMESTON CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-05-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




LAURENS CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-08-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SCHENEVUS CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-09-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MILFORD CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-11-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MORRIS CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-12-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ONEONTA CITY SCHOOLS FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-14-00-01
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           Valley View Elementary:
01-0604    Reconstruction               0-004-003  07/12/02   16                             0      177,492     /  /                /  /     07/02/08    10/07/05  MGL
03-0728    Reconstruction               0-004-005  04/25/04   7,10,155,15,16         1,427,757    1,429,246   11/10/09    AJP     11/10/09   07/02/08    08/30/05  DDJ

           Center Street Elementary:
01-0605    Reconstruction               0-006-006  07/12/02   16                       224,474      224,474   03/17/09    AJP     03/17/09   07/02/08    10/07/05  MGL
03-0729    Reconstruction               0-006-009  04/25/04   2,4,7,8,9,10,14,155,   1,336,913    1,342,924   11/03/09    AJP     11/03/09   07/02/08    08/30/05  DDJ

           Great Plains Elementary:
01-0606    Reconstruction               0-017-006  07/12/02   16                       143,121      164,917   03/18/09    AJP     03/18/09   07/02/08    10/07/05  MGL
03-0731    Reconstruction               0-017-008  04/25/04   2,4,8,9,10,155,15,16   3,030,117    3,042,932   11/12/09    AJP     11/12/09   07/02/08    08/30/05  DDJ

           Riverside Elementary:
01-0607    Reconstruction               0-018-006  07/12/02   16                       171,511      171,511   03/19/09    AJP     03/19/09   07/02/08    10/07/05  MGL
03-0732    Reconstruction               0-018-008  04/25/04   2,4,8,9,10,155,15,16   2,464,802    2,473,901   11/04/09    AJP     11/04/09   07/02/08    09/03/04  DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




UNATEGO (OTEGO-UNADILLA) CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-16-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           Otego Elementary School:
01-0531    Additions and Alterations    0-001-004  06/11/02   02 - 16                1,502,436    1,557,710   09/08/08    AJP     09/08/08   06/29/07    09/03/04  MAC

           Unadilla Elementary School:
01-0532    Additions and Alterations    0-009-006  06/11/02   02 - 16                1,976,669    1,986,229   09/15/09    AJP     09/15/09   06/29/07    09/03/04  MAC

           Bus Garage:
01-0537    Reconstruction               5-006-003  06/11/02   7,8,10,155               175,527      175,527   08/11/08    AJP     08/11/08   06/29/07    09/03/04  MAC


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




COOPERSTOWN CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-17-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




RICHFIELD SPRINGS CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-20-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CHERRY VALLEY-SPRINGFIELD CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-22-02-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WORCESTER CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 47-25-06-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition